Kolin Soma Coal Fired Power Plant

As TTM Enerji, we undertake electrical tests at Soma Kolin Thermal Power Plant (510MW). 

Our scope at Soma Kolin Power Plant is to performe;

  • generator circuit breaker tests
  • IPB and NSPB isolated phase bus duct tests
  • MV metalclad cubicle tests
  • MV motor tests
  • Power transformer test
  • Static VAR Compensation(SVC) system tests
  • XLPE cable tests
  • LV switchgear tests